Predecessor task slips
Exception
Situation
A predecessor Task is late and affects dependent Tasks.
Recommendation
Move the predecessor date, preview the dependent reschedule, check Milestones, log a Risk.
Why
Previewed rescheduling shows the full impact; affected Milestones need at_risk set by hand.
Steps
- Move the predecessor’s date.
- Preview and reschedule dependent Tasks.
- Check affected Milestones.
- Set at_risk if needed.
- Log a Risk.
Avoid
- Edit each dependent Task by hand without checking impact.
Roles & permissions
PM.