Workflows & examples
Two sample Manufacturing workflows: going from a BOM to finished goods, and going from scheduling to releasing orders to the shop floor.
Purpose
Show the continuous chain from the bill of materials (BOM) to a work order, consumption of raw materials in base units, receipt of finished goods into stock, and posting cost to Accounting.
When to use
- You are planning production of a product and need to know which materials will be consumed.
- You need to sequence work orders across work centers before releasing them.
- You want to follow progress and output once orders are on the shop floor.
Workflow 1: From BOM to finished goods
Maintain the BOM
Engineering maintains the product’s BOM with components, quantities and units of measure.
Create the work order
The planner creates a work order for a quantity; the BOM explodes into a material list.
Run production
Production runs — materials are consumed in base units and finished goods are received into stock.
Post cost
Work order cost accumulates and posts inventory valuation to Accounting.
Workflow 2: From scheduling to release
View the schedule
Open Manufacturing → Schedule to see planned work orders across work centers.
Adjust the sequence
Adjust the sequence manually if needed (the basic schedule does not check capacity; turn on capacity-based scheduling to sequence by work center and machine).
Release
Release the work order to the shop floor to start production.
Track
Track progress and output in Overview and Reports.
The basic schedule does not check capacity. If you need sequencing by work center and machine, turn on capacity-based scheduling before you release.
When materials are consumed, quantities are converted to the item’s base unit, so a BOM may be declared in a different unit of measure.