Tasks setup guide

This page walks through 6 steps to set up Tasks, in the order the in-app Setup assistant recommends. Each step lists what to prepare, the questions to answer first and the screen to use.

In the app, open Settings → Setup assistant: it measures your current state, asks the survey questions below and proposes a change set you approve before it is applied. This page is the read-only version for preparing ahead or doing it by hand.

Tasks setup guide
Tasks setup guide

1. Prepare

Optional

What to have ready before setting up Tasks: the company-wide task rules in Settings, the working calendar, and the list of open work.

#TaskHowScreen
1Company-wide task rules decidedSettings → Others configuration: sub-tasks, dependencies, time tracking, required assignee/due date, comment on status change./settings/others-configuration
2Working calendar confirmedHR settings: working schedule and holidays — capacity, due dates and dependency shifts count working days./hr/settings
3Open-work list readyTitle, project, assignee, due date, status and priority of the work still open.—
Prepare
Prepare

2. Task rules

Required

Choose how tasks are assigned, reviewed and linked: workload when assigning, co-work estimates, the review gate and its scores, sub-task and dependency rules, and the priority score.

Prepare first

  • A short description of how work is handed out and closed today: who assigns, whether several people share a task, whether someone checks the result before it counts as done.
  • A decision on whether sub-tasks and task dependencies are used — they are switched on in Settings → Others configuration before their rules here mean anything.

Questions to answer

  • When you assign a task, should people see the assignee’s workload, and be warned before overloading someone? Do several people often share one task?
  • Must finished work be reviewed and scored before it counts as done? May someone review their own task, and should only the named reviewer decide?
  • Should task review scores count towards employees’ performance (and so towards pay)?
  • Do you split tasks into sub-tasks? Must sub-tasks stay within the parent dates, and how should parent progress be shown?
  • Do tasks depend on each other (one cannot start before another finishes)? Should dependent tasks move automatically when dates slip, even across projects?
ToggleKeyDefaultEffect
Show workload when assigningtasks.assignee_capacity_checkShow informationShow: the people picker shows assigned hours / capacity in the task window. Warn: ask again when the person goes over capacity. Off: hidden.
Estimated hours with several people (co-work)tasks.co_worker_estimate_modePer personPer person: enter hours for each person; people without an entry share the rest evenly. Split evenly: the task estimate is divided equally.
Advanced task managementtasks.advanced_managementOffCompleted work must be submitted for approval: the assignee submits, a reviewer scores the configured criteria and approves or requests revision before the task can be marked done.
Allow reviewing your own tasktasks.review_self_approval_allowedOffWhen off, the person assigned to a task cannot approve their own submission (separation of duties).
Only the designated reviewer can reviewtasks.review_restricted_to_reviewerOffWhen off, anyone with the tasks:approve permission can decide a submitted task even though the task names a reviewer.
Feed review scores into Performancetasks.review_feeds_performanceOffApproved task-review scores become the employee’s task_review_score KPI. That KPI prefills the Completion Evaluation, which feeds payroll — leave it off to keep the review gate purely a workflow control.
Sub-tasks inherit from the parenttasks.subtask_inherit_defaultsOnWhen creating a sub-task with empty fields: take the parent project, deliverable, assignee, priority and date window. The user can still change them.
Sub-task dates outside the parent datestasks.subtask_dates_within_parentWarn — still saveWarn: save and notify; Block: refuse to save; Off: no check.
Parent task progresstasks.parent_progress_modeManualManual: keep the % the user declared. Roll up by estimated hours / by count: also show a % computed from sub-tasks (never overwrites the declared %).
Start the parent when a sub-task startstasks.parent_auto_start_with_subtaskOnWhen the first sub-task moves to In progress, a parent still in Backlog/To do moves to In progress too.
Starting a task with unfinished dependenciestasks.dependency_start_policyWarn — ask for confirmationApplies the first time a task leaves Backlog/To do (to In progress, In review or Done). Finish→start: the predecessor must be done; start→start: it must have started. Sub-tasks inherit their parent’s dependencies. Off: no check; Warn: ask and allow; Block: refuse.
Allow dependencies across projectstasks.dependency_cross_project_allowedOffOn: a task may depend on a task of another project. Off: same project only (a task without a project links only to tasks without a project).
Reschedule dependent taskstasks.auto_reschedule_dependentsAsk before shiftingWhen dates change or a link is added (also on create and bulk edit) and a dependent now starts too early. A due date is the last working day, so finish→start means the day after. Ask: propose and wait for confirmation; Automatic: shift right away (duration kept, finished tasks and undated tasks never moved); Off: never shift — only a warning.
Automatic priority scoretasks.priority_scoringOffCompute a 0–100 priority score for each task from Impact, Urgency and Effort. Urgency and effort are derived from the due date and estimate; impact from project priority, OKR links and blocked tasks, or entered by hand. The formula and derivation rules are configured per company, with a preview before applying. Requires Advanced task management.
Task rules
Task rules

3. Task owners

Required

Choose who owns Tasks: the operations manager and the PMO administer Tasks settings; project managers and team leads hand out and review work. You cannot remove a person’s last role here.

Prepare first

  • The list of who owns the Tasks settings and who hands out and reviews work (project managers, team leads) — each must already be invited as a user.

Questions to answer

  • Who owns how tasks work across the company (settings, review rules)?
  • Who hands out work and checks it before it is done — project managers, team leads?
Role templateKeyFor
Operations Manageroperations_managerOperations manager: owns Tasks settings and review rules
Project Portfolio Managerproject_portfolio_managerPMO: also administers Tasks settings
Project Managerproject_managerProject manager: hands out and reviews work on projects
Team Leadteam_leadTeam lead: hands out and reviews the team’s work
Task owners
Task owners

4. Task types & criteria

Optional

Review the task types, and if reviews are on, the scoring criteria. Each button opens the existing editor; counts come from real data.

Prepare first

  • The task types the business really uses (Vietnamese and English names) and, if reviews are on, the scoring criteria and their weights.

Questions to answer

  • Which kinds of work do you track as tasks (development, support, admin…), and how should a reviewer score finished work?
#TaskHowScreen
1Task typesTasks settings → Master data. Shared with Projects, so only IT can edit them./tasks/settings
2Review criteriaOnly if review is on: Tasks settings → Feature toggles; active weights must total 100%./tasks/settings
3Sub-statuses (optional)Tasks settings → Master data, e.g. “waiting for customer” under In progress./tasks/settings
Task types & criteria
Task types & criteria

5. Open work

Optional

Bring the work still open on the cut-over date into XBuddy; finished work stays in the old tool.

Prepare first

  • Agree the cut-over date: work still open on that day is brought into XBuddy; finished work stays in the old tool.
#TaskHowScreen
1Open tasksCreate (or import from the task list) the tasks still open, with assignee and due date./tasks
Open work
Open work

6. Trial run

Optional

Run one real task end to end before going live and check each result with the key user.

Prepare first

  • Use one real task with two people and one sub-task; agree with the key user who checks each result.
#TaskHowScreen
1Assign a taskThe people picker shows workload as configured and the assignee gets a notification./tasks
2Sub-task and dependency rulesOnly if they are on: a sub-task outside the parent dates and a dependency warn or block as configured./tasks
3Review a finished taskOnly if review is on: submit, score as the reviewer and approve — it moves to Done; self-approval is refused when off./tasks
4Check an employee loginAn ordinary employee sees only the tasks their scope allows and cannot change Tasks settings./tasks
Trial run
Trial run

Next

See the feature pages of this app in the left menu, or the setup guides of every app.